Contract guide · JCT

JCT contract administration, notices and key deadlines.

How JCT contracts work, where they are used, and what contractors and employers each need to watch for, including the changes in JCT 2024.

JCT obligations

JCT expects notice as soon as it is apparent.

JCT ties extensions of time and loss and expense to prompt notice and good supporting information. Many JCT contracts are amended to turn those duties into strict time bars.

Extension of time

Notify delay forthwith.

When it becomes reasonably apparent that progress is or is likely to be delayed, the Contractor gives notice straight away, with the cause and the Relevant Event behind it.

Loss and expense

Claim loss and expense early.

Loss and expense notices are due as soon as the likely effect of a Relevant Matter becomes apparent, followed by supporting information and regular updates.

JCT 2024

Faster decisions in JCT 2024.

JCT Design and Build 2024 cuts the period for an interim extension of time decision from 12 weeks to 8, and JCT 2024 adds epidemics, asbestos, contamination and unexploded ordnance as Relevant Events.

Where JCT is used

The most widely used building contracts in the UK.

JCT forms are used across UK building work, public and private. Design and Build is the most common, with the Standard Building Contract for traditional procurement and Minor Works for smaller jobs.

Commercial and offices
Residential
Retail and leisure
Education
Refurbishment and fit-out
Contractor side

Contractor

Benefits
  • ✓
    Familiar to most UK clients, consultants and supply chains.
  • ✓
    JCT 2024 adds epidemics, asbestos, contamination and unexploded ordnance as Relevant Events.
  • ✓
    Interim extension of time decisions are now due within 8 weeks rather than 12.
  • ✓
    Loss and expense is recoverable for listed Relevant Matters.
Watch out for
  • !
    Delay notices are due forthwith once delay becomes reasonably apparent.
  • !
    Loss and expense notices need supporting information and regular updates.
  • !
    Schedules of amendments often add strict time bars.
  • !
    Under JCT Design and Build, the Contractor takes responsibility for completing the design in accordance with the contract.
Client side

Employer, Employer's Agent or Contract Administrator

Benefits
  • ✓
    Design and Build gives a single point of responsibility.
  • ✓
    JCT 2024 makes collaborative working a core obligation.
  • ✓
    JCT 2024 allows notices by email where the email addresses are set out in the Contract Particulars, which reduces disputes over whether notice was given.
  • ✓
    A form most of the market accepts, which keeps procurement simple.
Watch out for
  • !
    Extension of time decisions must be made within set periods.
  • !
    Late information, instructions and variations are Relevant Events and Relevant Matters.
  • !
    Liquidated damages need the right certificates and notices before they are deducted.
  • !
    Weak records make claims harder to assess and defend.

JCT questions

What is JCT?

The Joint Contracts Tribunal publishes the most widely used standard building contracts in the UK. The current edition is JCT 2024.

Which JCT contract should be used?

Design and Build is used when the Contractor designs the works. The Standard Building Contract suits traditional procurement, where the Employer's team completes the design. The Intermediate and Minor Works contracts suit simpler and smaller projects.

What is the difference between a Relevant Event and a Relevant Matter?

A Relevant Event can entitle the Contractor to an extension of time. A Relevant Matter can entitle the Contractor to loss and expense. Some causes, such as variations, appear on both lists.

What changed in JCT 2024?

JCT 2024 makes collaborative working a core obligation, adds new Relevant Events and Matters such as epidemics, asbestos, contamination and unexploded ordnance, cuts the interim extension of time decision period in Design and Build from 12 weeks to 8, and allows notices by email where the addresses are set out in the Contract Particulars.

How quickly must a JCT extension of time notice be given?

Forthwith, once it becomes reasonably apparent that progress is being or is likely to be delayed. Many amended JCT contracts replace this with a fixed time bar, so always check the amendments.

What is the extension of time decision period under JCT Design and Build 2024?

The Employer has 8 weeks to make an interim extension of time decision under Design and Build 2024, down from 12 weeks in the 2016 edition. The final review timetable is unchanged.

Contract terms vary by edition and are frequently amended. Always check the contract and any project-specific amendments that apply. This guide is general information, not legal advice.